Metro Cites Old Oil Wells as Century City Subway Needs $300 Million More
A Metro committee raised the D Line Section 2 budget to $2.87 billion, with the Century City station now aimed at early fall 2027.

Two abandoned oil wells under Beverly Hills High School sat in the path of the D Line subway's tunnels to Century City. Streetsblog Los Angeles reported Monday that working around them is one reason Metro's Finance Committee approved raising the 2.5-mile Section 2 budget by $300 million last week, from $2.57 billion to $2.87 billion.
Tim Lindholm, Metro's chief program management officer, told the committee it's the "final budget increase," Streetsblog reported. In his telling, the overrun is ordinary: he pointed to a 2020 Federal Transit Administration study that put the average cost growth on heavy rail subway projects at 42%. The line's own first leg, from Koreatown to Beverly Hills, ran about 25% over before it opened in May.
The rest of Metro's list is just as underground: stronger seismic lining for the tunnels, a Century City station shifted to avoid more old wells, a storm drain rerouted and construction limits imposed by Beverly Hills.
The full Metro board still has to approve the money at its Dec. 3 meeting. At the groundbreaking in early 2018, Metro's forecast had Section 2 carrying riders by 2025. Lindholm now expects early fall 2027, and late fall for the next leg to Westwood. That's when Century City gets its 20-minute ride to downtown, two years after the opening Metro forecast at groundbreaking.
Source: la.streetsblog.org, retrieved November 23, 2026.
™